Georgia Tech Procurement Assistance Center

  • Home
  • About Us
  • Training
    • Class Registration
    • On-demand Training
  • Useful Links
  • Team Directory
    • Albany Counselor
    • Atlanta Counselors
    • Augusta Counselor
    • Carrollton Counselor
    • Columbus Counselor
    • Gainesville Counselor
    • Savannah Counselor
    • Warner Robins Counselor
  • Directions
    • Atlanta – Training Facility
    • Atlanta – Office
    • Albany
    • Augusta
    • Carrollton
    • Columbus
    • Gainesville
    • Savannah
    • Warner Robins
  • New Client Application
  • Contact Us

Formal claim required to appeal negative performance evaluation

October 10, 2017 By Nancy Cleveland

For federal contractors, it is not an exaggeration to say that performance evaluations are the lifeblood of the business.

A less-than-satisfactory evaluation in the Contractor Performance Assessment Reporting System (CPARS) affects far more than just the agency’s assessment of performance on a particular project.  A negative evaluation follows a contractor around – impacting the ability to obtain future contracts due to the specter negative past performance ratings.

The good news for contractors is that the ability to challenge and – if successful – reverse negative CPARS evaluations is a quickly developing area of government contracting law.

The first step in any successful CPARS challenge involves meaningful participation in the evaluation process.  The Federal Acquisition Regulation (FAR) Part 42.15 entitles contractors to submit comments and receive an agency review of a disputed performance evaluation.  Specifically, contractors are entitled to submit comments, rebuttal statements, and/or other information in response to the agency’s evaluation.  The agency must then review those comments at a level above the contracting officer and update the evaluation, if necessary.

Keep reading this article at: https://governmentcontracts.foxrothschild.com/2017/09/articles/contract-claims/cpars-challenge-primer-formal-claim-required-to-appeal-negative-performance-evaluation/

Filed Under: Contracting Tips Tagged With: Contract Disputes Act, contractor performance, Court of Appeals, Court of Federal Claims, cpars, delays, differing site conditions, evaluation, evaluation criteria, FAR, past performance, performance, proposal evaluation, site conditions

When is an unforeseen condition a ‘differing site condition’?

August 25, 2017 By Nancy Cleveland

I was reviewing various articles I have written over the years and came across a prior version of this one about differing site conditions, written nearly twenty years ago.   I was curious – does this cup still hold water?

It does.

Many construction contracts contain some version of a “differing site conditions” clause.   It is found in the current version of AIA’s A201 general conditions, as well as in the EJCDC equivalent.   It also appears in most state DOT specifications, as well as in federal government construction contracts.   Generally, it provides for a change order (subject to procedural compliance) when the contractor encounters (i) subsurface or other concealed conditions that differ materially from the conditions indicated by the contract documents or (ii) unknown physical conditions of an unusual nature differing materially from those ordinarily encountered and recognized as inherent to the work provided for in the contract documents.   But, as they say, “timing is everything.”   This adage applies, too, to a differing site conditions claim.

In Olym­pus Corp. v. United States, 98 F.3d 1314 (Fed. Cir. 1996), the United States Federal Circuit Court of Appeals was confronted with the following ques­tion: Are delays caused by a govern­ment caused hazardous materi­als spill compensable under the federal Differing Site Condi­tions clause?  The court an­­­­­s­wered “no” based on its con­clusion that to be con­sidered a differing site con­dition, the condition must exist at the time the contract was formed.

Olympus entered into a fixed price contract with the United States to pave the plant yards at the Stratford Army Engine Plant located in Strat­ford, Connecticut. As man­­­­­­­­­­­­­dated by the Federal Acquisition Regulation, 48 C.F.R. ‘ 52.236-3 (1995), the contract contained a standard Differing Site Conditions clause which provided, in part, for an equitable adjustment, upon notice, of  “subsurface or latent physical conditions at the site which differ materially from those indicated in [the] contract.”

Keep reading this article at: http://www.jdsupra.com/legalnews/when-is-an-unforeseen-condition-a-73987/

Filed Under: Contracting Tips Tagged With: contract clauses, contract formation, differing site conditions, equitable adjustment, FAR, latent physical condition, postaward, site conditions, unforeseen condition

Contractor’s lackadaisical proposal preparation sinks its claim for costs

July 24, 2017 By Nancy Cleveland

To federal construction contractors, the true legwork may seem to begin only after the government has accepted a proposal and performance has begun. However, a recent Armed Services Board of Contract Appeals (ASBCA) decision reinforces that federal construction contractors’ work often should begin long before contract award.

In Zafer Construction Company, ASBCA No. 56769 (2017), the ASBCA rejected a construction contractor’s allegations of unilateral mistake, unconscionability, and differing site conditions (among other claims for additional costs). The problem? The contractor did not attend a government scheduled site visit, conduct an independent site visit, review technical drawings, submit any inquiries during the proposal stage, or otherwise take reasonable steps necessary to better ascertain the nature of the work prior to submitting a multimillion dollar proposal on a complex project.

By way of background, the contract in Zafer involved the U.S. Army Corps of Engineers’ procurement of renovation work at the Afghanistan National Military Hospital in Kabul, Afghanistan. In 2004, the buildings at this site had fallen into varying states of disrepair. In preparation for issuing the solicitation, the government employed an assessment team (called the Baker team) to survey the site, assess the condition of the buildings and infrastructure, and prepare a report for the government’s use in budgeting and defining the scope of work.

Keep reading this article at: http://smallgovcon.com/claims-and-appeals/contractors-lackadaisical-proposal-preparation-sinks-its-claim-for-costs/

Filed Under: Contracting Tips Tagged With: ACE, allowable costs, Armed Services Board of Contract Appeals, Army Corps of Engineers, ASBCA, claim, GAO, mistake, site conditions

Differing site conditions claims: Focus on actual costs incurred

March 15, 2016 By Nancy Cleveland

Today, we have a question for our federal construction readers:

If your project is operating within an anticipated budget, are you still entitled to the additional costs associated with a differing site condition? 

Recently, the Civilian Board of Contract Appeals (CBCA) answered our question with a resounding yes.

hardhatThis point is particularly important in the context of requests for equitable adjustments or claims asserted against the government.  You may think (or the government may try to convince you) that there is no entitlement when the project is below budget.  That is simply not the case.  The CBCA decision makes the point that damages are based upon the actual cost of performance — your bid should not be used against you.  In short, extra costs due to differing site conditions should always be tracked and documented — even if you are meeting or below a projected budget.

The case in question involved construction contractor Tucci and Sons Inc., which filed a claim seeking more than $80,000 on a DOT Federal Highway Administration (FHWA) contract for the reconstruction of a 9.7 mile stretch of highway in Mount Rainier National Park.  Tucci claimed that it experienced extra costs based on the unexpected need to work around a number of larger boulders impeding the work.

Keep reading this article at: http://www.mondaq.com/article.asp?articleid=470494

Filed Under: Contracting Tips Tagged With: actual cost, CBCA, Civilian Board of Contract Appeals, claim, construction, cost, damages, delays, FHWA, site conditions

Federal Circuit’s Metcalf decision a big win for contractors

May 15, 2014 By ei2admin

In a recent decision, the U.S. Court of Appeals for the Federal Circuit (“CAFC”) the supervising court for the Court of Federal Claims and the Boards of Contract Appeals, among others) clarified important legal principles concerning the federal government’s duty of good faith and fair dealing and its responsibility for differing site conditions. Metcalf Construction Company, Inc. v. United States controls disputes with the federal government and also provides authority and rationale useful to contractors in disputes with any project owner, public or private.

In October 2002, Metcalf Construction, a small business based in Hawaii, was awarded a $48 million contract to design and build 212 housing units for the U.S. Navy on a Marine Corps base in Hawaii. Saying the project did not go smoothly is an understatement. Metcalf’s performance was hindered and delayed by unanticipated soil conditions and other issues made worse by the Navy’s failure to administer the contract fairly and according to its terms. By the time the Navy finally accepted the project as complete in March 2007, almost two full years after the original completion date, Metcalf had incurred costs in excess of $76 million — leaving the contractor with losses of approximately $27 million.

Keep reading this article at: http://www.mondaq.com/unitedstates/x/311802/Building+Construction/Federal+Circuits+Metcalf+Decision+a+Big+Win+for+Contractors&email_access=on

Filed Under: Contracting News Tagged With: claim, contract administration, contract dispute, Court of Appeals, Court of Federal Claims, fair treatment, good faith, Marine Corps, Navy, price adjustment, reasonableness, recovery, site conditions

Recent Posts

  • Contractors must update EEO poster
  • SBA scorecard shows federal government continues to prioritize small business contracting
  • The risk of organizational conflicts of interest
  • The gap widens between COFC and GAO on late is late rule
  • OMB releases guidance related to small business goals

Popular Topics

8(a) abuse Army bid protest budget budget cuts certification construction contract awards contracting opportunities cybersecurity DoD DOJ False Claims Act FAR federal contracting federal contracts fraud GAO Georgia Tech government contracting government contract training government trends GSA GSA Schedule GTPAC HUBZone innovation IT Justice Dept. marketing NDAA OMB SBA SDVOSB set-aside small business small business goals spending subcontracting technology VA veteran owned business VOSB wosb

Contracting News

SBA scorecard shows federal government continues to prioritize small business contracting

OMB releases guidance related to small business goals

OMB issues guidance on impact of injunction on government contractor vaccine mandate

Changes coming to DOD’s Cybersecurity Maturity Model Certification under CMMC 2.0

Judge issues nationwide injunction halting enforcement of COVID-19 vaccine mandate

Read More

Contracting Tips

Contractors must update EEO poster

The risk of organizational conflicts of interest

The gap widens between COFC and GAO on late is late rule

Are verbal agreements good enough for government contractors?

CMMC 2.0 simplifies requirements but raises risks for government contractors

Read More

GTPAC News

VA direct access program events in 2022

Sandia National Laboratories seeks small business suppliers

Navy OSBP hosting DCAA overview (part 2) event Jan. 12, 2022

Navy OSBP hosting cybersecurity “ask me anything” event Dec. 16th

State of Georgia hosting supplier systems training on January 26, 2022

Read More

Georgia Tech News

Undergraduate enrollment growth reflects inclusive excellence

Georgia Tech delivers $4 billion in economic impact to the State of Georgia

Georgia Tech awards first round of seed grants to support team-based research

Georgia Tech announces inaugural Associate Vice President of Corporate Engagement

DoD funds Georgia Tech to enhance U.S. hypersonics capabilities

Read More

  • SAM.gov registration is free, and help with SAM is free, too
APTAC RSS Twitter GTPAC - 30th Year of Service

Copyright © 2023 · Georgia Tech - Enterprise Innovation Institute