In Creative Management Services, LLC, dba MC-2 v. U.S. (Feb. 26, 2021), the Federal Circuit affirmed a Court of Federal Claims decision dismissing a contractor’s appeal of the government’s Contract Disputes Act (CDA) claim as untimely, holding that the contractor appealed more than 12 months after receiving a contracting officer’s (CO) final decision. On appeal, the contractor alleged that the final decision was not a valid claim because it did not state a “sum certain” as required by the CDA, and this deficiency meant that the 12-month appeal period had not started to run.
Continue reading at: Crowell Moring